Status Update: Awaiting Developer Approval

We are getting closer to our site start, so I thought it would be a good idea to start posting regular status updates.

For the few weeks since our contract appointment, we have been fixing mistakes with our contract and house plans (and there have been a lot of them), and now we are finally at the stage of awaiting developer approval. Because our estate has covenants in place (e.g. rules about the facade, fencing etc.), they have to give the all-clear before we can go to site.

Porter Davis came back to us last week to advise us that they had to submit an updated landscape plan for the back fence (even though they aren’t building it), however, we were sent the same one we signed at the contract meeting, and I had to tell them it was incorrect.

This happened approximately a week ago, and so now we are waiting again – hoping to have the all clear this week.